- Operation Plan
- Yes
- Operation Comments
- Operational plan prepared by Geosyntec Consultants, dated 5/3/2006. See External Source Data for plan.
Tide gate not fully open during the site visit; open roughly 3'.
- Gate Comments
- Tide Gate installed on downstream side of culvert. It is a combination sluice gate and flap gate. When closed, the flapper feature of the gate permits outflow from the upstream marsh. Operated manually via hanwheel on top of the culvert headwall.
- External Data Comments
- Skaket Beach Road Slide/Flap Gate Operations Plan 07.12.2006
Skaket Beach Road Slide/Flap Gate Final Assessment Report 07.12.2006
US ACOE CENAE-R-2006-2314 Permit 2.13.2007
US ACOE CENAE-R-2006-2314 Letter of Non-Compliance 12.12.2008