TideGateway

Quincy-03

Broad Street

Quincy, Town River Bay

42.256124, -70.993907

Technical Specifications

Basic Properties

Type
Flap Gate
Material
Metal
Condition
Good
Geometry
Rectangular
Status
Active
Number of Gates
0

Operator & Management

Operator Type
PUBLIC
Operator
Town of Quincy
Permits
ACOE
Purpose
Flood Protection

Dimensions & Elevations

Dimensions
4ft diameter, 4ft height
Invert Elevation
-2.08 NAVD88
Tidal Influence
Upstream: N/A NAVD88, Downstream: 5.5 NAVD88

Culvert Details

Restriction Type
Roadway
Geometry
Rectangular
Material
Concrete
Number of Pipes
0
Dimensions
4ft diameter, 4ft height
Condition
Good
Comments
Culvert was embedded into a concrete headwall that appeared to have been recently installed and was in good condition.

Historical Records

Legacy data from previous surveys and documentation

Environmental Data

Invasive Species
No
Restoration Status
Not Applicable
Invasive Comments
N/A no upstream impounded area was present at this site. Could not locate where stormwater system daylights upstream.

Notes & Comments

General Comments
Tide gate easily accessible and located at bottom of new headwall at the northern end of Broad Street.
Operation Plan
No
Operation Comments
Tide gate appeared to be installed for the sole purpose of flood protection and conveying stormwater outflows.
Gate Comments
Tide gate appeared to have been recently installed and was in good condition.
Elevation Comments
Staining was apparent on the downstream (D/S) end of the headwall (HW) so approximate extent of U/S and D/S tidal influence was able to be assessed in addition to tide gate (TG) invert elevations. Tide gate was located at the outfall of a stormwater infrastructure network so there was not upstream area to assess. The below lists measuredowns taken with a surveyors rod and corresponding top of headwall LiDAR elevations (NAVD88 datum). 1) TG Inv: Top of HW El (D/S) = 8.00’; Inv Measuredown = 10.08’; TG Inv = 8.00 – 10.08 = -2.08’ 2) Upstream Tidal Influence: Top of headwall LiDAR Elevation = N/A; Staining Measuredown = N/A; U/S Tidal influence = N/A. 3) Downstream Tidal Influence: Top of headwall LiDAR elevation = 10.08’; Staining Measuredown = 4.58’; D/S Tidal Influence = 10.08’ – 4.58’ = 5.50’
External Data Comments
US ACOE NAE-2012-353 Permit Application 2.27.2012 US ACOE NAE-2012-353 Permit 3.27.2012